A. Principles and Eligibility
1. Who is eligible to apply under this framework?
Approval is limited to tenants holding a valid lease agreement or emphyteutical deed with INDIS. Applicants must be fully compliant with their contractual obligations. Any tenant in breach of existing agreements must regularise their position before an application can be considered.
2. What are the four options available under the framework?
The framework provides four pathways depending on the tenant's title and intended use of the electricity generated.
Option 1 – Self-Consumption with Proxy Compensation (Emphyteutical Tenants)
The installation is primarily intended to satisfy the tenant's own electricity demand. Any excess electricity exported to the grid is compensated through the applicable national proxy mechanism.
Option 2 – Full Export under Feed-in Tariff (FIT) (Emphyteutical Tenants)
All electricity generated is exported to the grid under an approved FIT arrangement. The project is effectively a revenue-generating renewable energy installation rather than a self-consumption project.
Option 3 – Partial Export under Feed-in Tariff (FIT) (Emphyteutical Tenants)
Electricity generated is first consumed by the tenant, with surplus electricity exported to the grid under an approved FIT arrangement. This option combines energy savings with FIT revenue generation.
Option 4 – Self-Consumption for Lease Tenants
The installation is primarily intended to satisfy the tenant's own electricity demand. Surplus exports may benefit from the applicable national proxy compensation mechanism. FIT participation is not eligible under this option.
3. How are contract extensions treated where a PV project is being proposed?
The framework recognises that REWS-related commitments, compensation arrangements and, where applicable, Feed-in Tariff (FIT) schemes are typically based on a project horizon of up to twenty (20) years.
However, the existence of a PV installation or a PV application shall not create an automatic entitlement to:
Any request for an extension shall continue to be assessed on its own merits and in accordance with the normal INDIS contractual management framework, irrespective of whether a PV project is proposed or already installed.
Applicants are therefore expected to assess the viability of their investment based on the tenure available under their existing agreement and within the context of the applicable regulatory framework.
B. Energy Generation Scenarios and Compensation
4. What is meant by "excess via proxy" and "proxy mechanism only"?
This refers to the compensation mechanism established under the applicable national regulatory framework whereby electricity exported to the grid outside a Feed-in Tariff arrangement may be compensated through a market-based proxy mechanism.
INDIS does not establish, regulate or receive any share of such compensation.
5. What fees and charges apply under the framework?
Depending on the option selected, applicants may be subject to one or more of the following:
Administrative Fees
All scenarios are subject to an administrative fee reflecting the processing and technical assessment of the application. More complex scenarios involving FIT arrangements attract higher fees. Administrative fees will range between €500 and €2500 depending on the option.
Roof Rates
Applicable only to lease tenants. The roof rate reflects the use of INDIS-controlled roof space and is calculated on the roof area allocated to the tenant. This additional Roof Rate will amount to €3 per square metre per annum, increasing by 5% every three years.
Export-Related Charges
Certain FIT-based options are subject to export-related charges. Depending on the scenario, these may take the form of:
These will depend on the value of the investment, the power capability of the setup and the FIT rate targeted.
Infrastructure Costs
Any required substations, upgrades, metering arrangements or related infrastructure works must be funded by the tenant.
The overall charging structure is intended to encourage self-consumption whilst ensuring equitable use of State-owned assets.
6. What is the difference between Option 1 and Option 3?
While both options permit self-consumption with export of surplus electricity, the distinction lies in how exported electricity is compensated.
Option 1 is a self-consumption model. Any excess electricity exported to the grid is compensated solely through the applicable proxy mechanism. Export is incidental to the primary objective of meeting onsite energy needs.
Option 3 allows the tenant to participate in a formal Feed-in Tariff arrangement, whereby exported surplus electricity generates income through an approved FIT mechanism. Since revenue is being generated from surplus exports, a different charging structure applies.
In summary:
7. Why has the Full Export FIT option been introduced?
While self-consumption remains the preferred and most sustainable model, certain projects may not be economically viable solely through onsite consumption.
The Full Export FIT option provides an alternative route for tenants whose consumption levels are insufficient to support a self-consumption installation or who wish to monetise available roof space.
To reflect framework priorities, this scenario is intentionally the least incentivised and is therefore subject to the highest administrative fee and a fixed annual charge.
8. In the Partial Export FIT scenario, must onsite demand be satisfied before electricity is exported?
Yes.
The Partial FIT arrangement inherently operates on this principle. Electricity generated onsite is first consumed by the facility and only surplus electricity exported to the grid generates FIT-related revenue.
The applicable energy bills serve as the basis for distinguishing between self-consumed and exported electricity.
9. Can tenants move between options over time?
Yes.
The framework recognises that operational requirements, energy consumption patterns, technological developments and energy efficiency improvements may evolve over time.
A tenant may move between eligible options provided that all applicable approvals are obtained and any new regulatory requirements are satisfied.
Where a change requires a new REWS application or a new electricity meter, it will be treated as a new application under the framework, subject it is still within the eligible parameters.
C. Charges and Financial Treatment
10. Why do exported electricity charges differ between the Full Export and Partial Export FIT scenarios?
The distinction reflects the nature of each arrangement.
For Full Export FIT, the tenant elects to export all electricity generated. A fixed annual charge is established in advance based on project size, investment value and financial modelling.
For Partial FIT, a percentage-based charge applies only to revenue generated from exported electricity, ensuring that self-consumed energy is not penalised.
11. How does INDIS ensure rooftop potential is fully utilised for lease tenants who are not eligible for FIT?
Lease tenants continue to have the opportunity to maximise self-consumption and may benefit from any applicable proxy compensation mechanism for surplus electricity exported to the grid.
The framework allows lease tenants to size and operate their installations in a manner that significantly reduces their electricity costs and, where technically feasible, enables them to achieve net-zero electricity consumption from the grid.
12. Is the Full Export FIT charge fixed or variable?
The annual charge is fixed.
Financial modelling, including projected Internal Rate of Return (IRR), may be used to establish the charge during the assessment phase. However, once approved, the charge remains fixed and does not fluctuate based on project performance.
D. Technical Requirements and System Changes
13. How are system upgrades, panel replacement and technological improvements treated?
Routine maintenance remains the responsibility of the tenant and does not require a new application.
However, the following are considered material modifications and require approval:
Such cases are treated as new applications.
14. Why is the framework limited to rooftop installations?
The current framework focuses on rooftop installations.
Façade-mounted installations and other technologies may be considered in future revisions as experience is gained and the regulatory environment evolves.
15. Does the roof rate apply only to the area occupied by PV panels?
Yes.
The roof rate applies only to the area physically occupied by the PV installation footprint and does not extend to unused roof space.
Any future expansion of the installation footprint may require a review of the area occupied and the corresponding roof rate applicable at that time.
16. Who bears the cost of substations and related infrastructure?
Any substation costs, upgrades to distribution infrastructure, metering requirements or associated electrical works required by the project are borne entirely by the tenant.
This follows the same principle applied to other operational infrastructure requirements and is not unique to PV projects.
E. Roof Rights, Multiple Occupancy and Shared Infrastructure
17. Can roof space be leased to third parties?
No.
Only direct investment by the tenant holding the relevant lease or emphyteutical agreement is permitted. Third-party agreements, leasing arrangements and similar structures are not permitted under the current framework.
18. How are buildings with multiple tenants treated?
Such situations are currently expected to be limited across the industrial estate portfolio.
Where technically feasible and structurally appropriate:
Where circumstances are more complex, INDIS may determine the most appropriate allocation methodology on a case-by-case basis.
Furthermore, where a building, zone or cluster of units presents challenges in allocating roof space fairly and efficiently, INDIS may elect to treat the area as a single renewable energy project. In such cases, the project may be planned, procured, managed and controlled directly by INDIS through a separate framework designed to ensure equitable access and optimal utilisation of available roof space.
F. Compliance and Exit Arrangements
19. How will INDIS enforce compliance?
Compliance may be enforced through:
Failure to comply with framework obligations may result in enforcement measures available under the relevant agreements.
20. What happens if a tenant winds up operations or vacates the premises before contract expiry?
The PV installation remains the tenant's investment and responsibility.
Accordingly, the tenant (or liquidator, where applicable) is expected to remove the installation and comply with any reinstatement obligations arising under the contract or framework.
Where removal is not practical or desirable, INDIS may, at its sole discretion, consider taking over the installation following an assessment of its technical condition, remaining useful life, operational suitability and legal implications.
21. Can electricity generated at one site be used to offset consumption at another site?
No.
The electricity meter must be registered in the name of the tenant and linked to the site at which the PV installation is located. Electricity generated under a particular project may therefore only be used in accordance with the applicable national rules governing that installation and meter.